Humidifier Process
During the humidification process steam fills the header, and then travels up the steam distributors and
through steam ejector eyelets. Condensate generated from heat transfer within the vertical tubes
accumulates at the bottom of the header.
PCR Process
- The header's integrated slope forces accumulated condensate to the drain port (1), which then flows
into the PCR tank (2)
- When the tank level setpoint is attained, the ESC controller opens the Steam supply valve (3) to
empty the PCR tank (2) into the Condensate return (5) system.
- The check valve (4) prevents steam pressure from reversing into the header.
- The ESC controller continues to monitor the tank's condensate level and temperature.
- When the PCR tank (2) is empty, the ESC controller closes the Steam supply valve (3) and opens
the Relief valve(6) to partially relieve pressure in the PCR tank (2) and allow the flow of condensate
from the header to the PCR tank (2).
- With the Relief valve (6) open, the check valve (7) prevents backflow from the Condensate return
(5) to the PCR tank (2).